# Cycle time

Understand how efficiently work moves through your team's process.

Cycle time is the total time a story or bug spends in the 'In progress' steps of its team's workflow. In the default workflow, these steps are 'Design', 'Development', 'Test', and 'Review', but cycle time works the same way for [customized workflows](https://docs.atono.io/docs/workflows).

Atono averages your team's cycle times for each story size and for bugs, and uses those averages for [projected completion dates](https://docs.atono.io/docs/estimated-completion-dates) and [staleness indicators](https://docs.atono.io/docs/staleness-indicator).

<br />

***

# How cycle time works

An item starts accumulating cycle time when it moves from a 'To do' step into an 'In progress' step, and stops when it moves into a 'Done' step. Items don't need to follow a straight path. They can move back and forth between steps, skip steps, or leave 'In progress' for a while. Cycle time pauses whenever an item is outside 'In progress' and resumes when it returns, so time in 'To do', 'Done', and 'Won't do' steps never counts.

Because cycle time measures how long work takes from start to finish rather than how many hours were worked, it includes nights and weekends. It can't be edited, but if an item's cycle time doesn't reflect typical work, you can mark the item as an [outlier](#outliers) to leave it out of the team's average cycle time and the reports.

<br />

## Cycle time is tracked per team

Each team tracks its own cycle time for an item. When a story or bug moves to another team, its cycle time on the new team starts at zero. If it later moves back to a team it was on before, the cycle time from that team returns, and tracking continues from there.

<br />

## Items created already in progress

When you create a story or bug in an 'In progress' step, you're asked when work on it started. Cycle time counts from the date and time you select, which can't be in the future, or from when the item is created if you leave them unchanged.

On Scrum teams, an item can only go into an 'In progress' step once it's in the active sprint.

<br />

***

# Cycle time on stories and bugs

A story's or bug's cycle time appears beside 'Cycle time' at the bottom of its details panel, and it's the cycle time for the team shown just above it. The value is shown in days and hours, rounded to the nearest hour, or as '< 1 hour' for shorter times.

While the item is in progress, its cycle time keeps accumulating. Once it's done, the value is the total time the item spent in progress on its current team. Hover over the value to see whether it's still accumulating or is the final total.

An item doesn't show any cycle time if it has never been in an 'In progress' step on its current team. That includes new items in 'To do', items that moved straight from 'To do' to 'Done', and items that just moved to a new team. Items in a 'Won't do' step don't show cycle time either.

If the item is marked as an outlier, '(excluded from cycle time reporting)' appears after its cycle time.

<Image src="https://files.readme.io/060db5fbd27ad2a96eda04b3da9352ef8ff6ff73f6fd3c9988875ae988a22815-image.png" align="center" width="300px" />

<br />

## Unavailable cycle time

'Unavailable' appears when an item was in progress and then moved back to a 'To do' step. The time it already spent in progress isn't lost. Once the item returns to an 'In progress' step, its cycle time shows again and picks up where it left off. If the item is an outlier, '(excluded from cycle time reporting)' appears after 'Unavailable' too.

<Image src="https://files.readme.io/8e9ca171ec68219b2ef7a1e363cf37dfb61802eef7eae5c61cba933b50e86c94-image.png" align="center" width="300px" />

<br />

***

# Average cycle time

Cycle time isn't meant to track the exact working hours for each item. Instead, the team's average cycle time for each type and size of work shows how long similar work typically takes.

Atono calculates a separate average for each story size, for unsized stories, and for bugs. Each average is the mean cycle time of the items the team completed within its [cycle time window](#configure-the-cycle-time-averaging-window), leaving out outliers.

Each average needs at least five completed items. If a story size has fewer than five, Atono uses the average for all of the team's completed stories instead, and if the team has fewer than five completed stories altogether, there's no average for that size. Bugs don't have a fallback, so there's no average for bugs until the team has completed at least five.

If a step in the team's workflow moves to a different category, cycle time that's already been recorded isn't recalculated, so averages based on earlier work stay the same. Only time from then on follows the step's new category. For more details, see [How categories impact cycle time](https://docs.atono.io/docs/workflows#how-categories-impact-cycle-time).

<br />

***

# Cycle time reports

Scrum and Kanban teams both have two cycle time reports:

* **Cycle time by workflow step**: Shows where stories and bugs spend their time while in progress, broken down by workflow step.
* **Cycle time over time**: Shows how the team's average cycle time for each story size and for bugs changes from one period to the next.

Both reports measure how long completed work spent in progress, while [Story throughput](https://docs.atono.io/docs/story-throughput) counts how much work was completed.

To open a cycle time report:

1. In the side menu, click the team.
2. Click the **View team overview** icon next to the team name.
3. Select the **Analytics** tab.
4. From the report selector, select **Cycle time by workflow step** or **Cycle time over time**.

<br />

## Cycle time by workflow step

The 'Cycle time by workflow step' report shows the average cycle time for each story size and for bugs completed during the 'Show last' timeframe, broken down by the steps in your team's workflow.

<Image src="https://files.readme.io/2c19a8058fcda5585248e81bdc46e0e1cd52244e0e4e6694b160c8f12a1c54f0-cycle-time-by-workflow-step.png" align="center" width="650px" />

Each row is a story size or bugs, starting with 'Unsized' and ending with 'Bugs' below a divider. Only sizes with completed items in the timeframe are shown.

Each bar is divided into the team's 'In progress' steps, in workflow order and in each step's color, so you can see how much each step adds to the total. The total average cycle time and the number of completed stories or bugs appear to the right of each bar.

Hover over a row to see a pop-up with:

* The story size, or 'Bugs'.
* The dates the timeframe covers.
* The number of completed stories or bugs.
* The average cycle time.
* The average time spent in each visible workflow step, and its percentage of the total.

Use the legend below the chart to show or hide workflow steps. Hiding a step removes it from every bar and recalculates the totals and percentages from the visible steps, while the number of completed items stays the same.

<br />

## Cycle time over time

The 'Cycle time over time' report shows how the team's average cycle time changes from one period to the next, for stories and bugs together.

<Image src="https://files.readme.io/708d8681eec994c537a105225240db251cf9d611028529aae133bcaef01caa42-cycle-time-over-time.png" align="center" width="650px" />

Each bar is a period within the 'Show last' timeframe. The length of each period depends on the timeframe:

* **1 month**: Daily.
* **2 to 7 months**: Weekly, in 7-day blocks that start on the same weekday as the timeframe.
* **8 to 31 months**: Monthly.
* **32 to 60 months**: Quarterly.

The first and last periods can be partial. Each bar is divided into story sizes and bugs, and each segment's height is that group's average cycle time for items completed in the period. Since the segments are stacked, a bar's total height adds the averages together rather than showing one overall average.

Hover over a bar to see a pop-up with the period's dates, and the average cycle time and number of completed items for each visible story size and for bugs.

Use the legend below the chart to show or hide story sizes or bugs. The legend only lists sizes with completed items in the timeframe.

<br />

### Calculation range

When 'Show last' reaches back further than the team's cycle time window, the chart shows which periods fall outside it.

Periods that end before the window starts appear faded. Hovering over one shows a note that its data isn't used to estimate completion dates or staleness indicators. Faded periods still count toward the report's values and are only left out of the team's average cycle time.

<Image src="https://files.readme.io/ae6a7ff77c4cb19d6a0400b02779a876c463666ffa9eea3397105f66e68b7d73-image.png" align="center" width="500px" />

A dashed line marks the period where the window starts.

<Image src="https://files.readme.io/226badaa17ba535149821ce207a61a34212c8f8820e0cca903ec08489f737c22-image.png" align="center" width="400px" />

<br />

***

# Interpret cycle time reports

<br />

## Show last

Use **Show last** to choose how far back the report goes, from 1 to 60 months or 1 to 260 weeks. The default is 3 months. Your selection is saved for you across all teams, and it's shared between the cycle time reports but not with Story throughput.

<br />

## Team time zone

'Cycle time over time' groups completed items into periods using the [team's time zone](https://docs.atono.io/docs/teams#set-team-time-zone), which the report's description names. When you open the list behind a period, its 'Completed' dates use the team's time zone too.

<br />

## View the work behind the data

Click a bar or segment to open the related completed stories or bugs on the [Everything](https://docs.atono.io/docs/everything) page, with these filters:

* The team, and stories or bugs.
* 'Workflow step', set to any step in the 'Done' category.
* The row's or segment's story size. Bugs don't get a size filter.
* 'Completed', set to the 'Show last' timeframe for 'Cycle time by workflow step', or to the period you clicked for 'Cycle time over time'.
* 'Outlier', set to 'No'.

In 'Cycle time by workflow step', every segment in a row opens the same list of the row's completed items, rather than the items in the step you clicked. The list can also include items that moved straight from 'To do' to 'Done', which the report leaves out because they have no cycle time.

If the team is private and you're not a member, clicking shows 'You don't have permission to view items on this team's backlog.' instead.

<br />

***

# Configure the cycle time averaging window

Change a team's cycle time window when older work no longer reflects how the team works, for example after a change in the team's members or process. The window decides which completed items count toward the team's [average cycle time](#average-cycle-time).

There are three options:

* **Default**: Items completed in the past six months, or since the team started if that's more recent.
* **Rolling range of months**: Items completed in a rolling window of 1 to 12 recent months.
* **Set a specific date**: Items completed on or after the date you select, which can't be in the future.

Workspace Owners, Administrators, and the team's team admins and backlog owners can change the window. Anyone can see the team's current window by hovering over the **info** icon next to the report selector on the Analytics tab.

To change the cycle time window:

1. In the side menu, click the team.
2. Click the **View team overview** icon next to the team name.
3. Click the **ellipsis** (...) icon in the header.
4. Select **Cycle time window**.
5. Select an option, and set the number of months or the date if needed.
6. Click **Save**.

The window affects everything that uses average cycle time, including projected completion dates and staleness indicators. It also affects the [estimate for unsized stories](https://docs.atono.io/docs/total-story-points#unsized-stories), which feeds into total story points and burndown charts. The Story throughput projection can use it too, to limit which periods it includes.

What the cycle time reports show depends on 'Show last', not the window. The window's only effect on them is the faded periods in [Cycle time over time](#calculation-range).

<br />

***

# Outliers

Mark a story or bug as an outlier when its cycle time is unusually long for reasons that don't reflect typical work, so it doesn't skew the team's averages.

An outlier is left out of the team's average cycle time, projected completion dates, staleness indicators, both cycle time reports, and the lists they open on the Everything page. It still counts in Story throughput. To find outliers, use the 'Outlier' filter on the Everything page.

Workspace Owners, Administrators, Product Managers, and the team's team admins and backlog owners can mark items as outliers. An item's outlier status is removed if it moves to another team.

<br />

## Mark an item as an outlier

1. On a story or bug, click the **ellipsis** (...) icon in the header.
2. Select **Mark as an outlier**.

<Image src="https://files.readme.io/794187c94aa10cc20c8ea642f73d2f0f1ae48b49ecd920cf2bf97c0a3d367951-mark-as-an-outlier.png" align="center" width="600px" />

<br />

## Remove outlier status

If you marked an item as an outlier by mistake or change your mind, remove its outlier status to include it in the team's averages and reports again.

1. On a story or bug, click the **ellipsis** (...) icon in the header.
2. Select **Unmark as an outlier**.